Technical Guide / AI Infrastructure
How to Evaluate an AI Colocation Site
A structured checklist for comparing AI colocation sites on power, cooling, network, operations, and the status of the capacity being offered.
GridColo Infrastructure Team 路 路 3 min read
AI deployments put unusual pressure on every layer of a data center. A site that works well for enterprise colocation may not be suitable for a dense training cluster, and a site marketed as 'AI-ready' may describe a plan rather than installed infrastructure. A disciplined evaluation separates what exists from what is intended.
1. Start with capacity status
Before comparing specifications, establish whether the capacity is operating, commissioned, under construction, in development, or still a concept. Each status carries different risk. Ask for the status in writing, and ask what milestones remain before your capacity is energized and accepted.
2. Power: source, topology, and delivery
- What is the power source鈥攗tility, on-site generation, or hybrid?
- What is the electrical topology and redundancy for your phase?
- Where is the demarcation point?
- What is the delivery schedule, and what does it depend on?
3. Cooling: posture and parameters
Ask whether the hall is air-cooled, liquid-ready, hybrid, or direct-to-chip capable鈥攁nd whether liquid distribution is installed or only provisioned. Request supply temperature, cooling ratio, and supported density for your phase, not for the site in general.
4. Network: inside and outside the cluster
Evaluate both the cluster fabric (pathways, row layout, distance limits) and the external network (entrances, carriers, route diversity, cloud access). Carrier neutrality is site-specific; confirm which carriers are present today.
5. Operations and accountability
- Who operates the facility, and who is your contractual counterparty?
- What does the remote hands catalog include?
- How are incidents communicated and reviewed?
- Is there a responsibility matrix for every operating layer?
6. Contract structure
Review how the MSA, service order, site exhibit, and SLA fit together. Service commitments should appear in the agreement, not only in marketing materials.
7. Record the evidence for each proposed phase
Copy one worksheet per proposal. For each answer record confirmed, unknown, or dependent, then name the evidence, evidence date, responsible party, and unresolved decision. Confirmed describes a supported fact, not a guarantee about future delivery. Dependent means the condition must be resolved before the proposed use; unknown must not be treated as zero or available.
| Review field | Question to resolve | Record |
|---|---|---|
| Phase and capacity | Which phase and customer allocation does the proposal cover? | Stage, readiness, commercial availability; evidence and status. |
| Power interface | Where is power delivered and metered under the proposed operating conditions? | Demarcation, allocation, operating limits, outstanding dependencies. |
| Cooling interface | Does the proposed equipment fit the actual thermal and fluid envelope? | Installed versus provisioned systems, customer work, acceptance evidence. |
| Network | Which endpoints, providers, and paths support the application? | Carrier presence versus remote reach, diversity evidence, delivery owner. |
| Operations | Who performs, approves, and supports each activity? | Named counterparty, responsibility schedule, service and exception records. |
| Delivery decision | What must be resolved before commitment and before handoff? | Owner and evidence for each open item; contractual dependencies. |
Hypothetical comparison: bigger is not necessarily deliverable
Proposal A advertises a larger future campus but has unresolved power and cooling interfaces for the requested phase. Proposal B describes a smaller phase with documented interfaces, yet still needs confirmation that an allocation is commercially available. Neither headline determines the winner. Compare the equipment fit and remaining dependencies against the required start conditions; do not mark either proposal ready until its supporting evidence covers the actual service.